Designed to be the world's highest-output fuel cell power generating facility, the 27-MW Red Lion Energy Center was engineered, procured and built in nine months.

Despite Bloom's distant headquarters, the team was able to maintain close coordination. Integrated review meetings between the owner, designers and contractors during the design phase led to continually evolving designs that were fully vetted by the client's engineering and manufacturing groups. The team was able to integrate alternatives early in the process, reducing the time and cost of design rework.

Project Included: 

  • Added 27-MW New Fuel Cell Generating Plant with 34.5kV Collector Circuits, Step up Substation and 69kV Transmission Line

  • Added New 69kV Tie Line at Existing Substation

  • Short Circuit Calculations

  • Load Flow and System Losses Calculations

  • Arc Flash Calculations

Red Lion Energy Center

CHECK OUT THE ARTICLE FROM ENR HERE

27-MW Red Lion Energy Center

SECo logo in white text

Headquarters

6 Commerce Drive

Reading, PA 19607

​​​

​      

              

© 2025 by Substation Engineering Company

© 2020 by Substation Engineering Co.

  • LinkedIn
  • Facebook

Headquarters

6 Commerce Drive

Reading, PA 19607

​​​

Phone: 610-603-5445

  • LinkedIn

Follow us:

Navigations

About 

Services

Projects 

Careers

Contact

Inquires

​​

Email info@subengco.com for more information.

Career Opportunities

To apply, please send resumes to our Human Resources Department: 

recruiting@subengco.com.

© 2023 by Substation Engineering Company

bottom of page